New Detached ADU in Paradise, NV: What the Build Actually Looks Like
A new detached ADU in Paradise, NV typically runs $45,000 – $130,000 and takes 4 – 7 months from the first permit application to final inspection, depending on size and finish level. The “detached” part matters: you’re building a separate structure on your lot, with its own foundation, utilities, and roof, not converting a garage or carving up interior square footage. Call (844) 797-4406 and we’ll walk your lot, check setbacks, and give you a written number before anyone swings a hammer.
How the Build Runs, Stage by Stage

Every detached ADU is a small house. That means the sequence doesn’t skip steps just because the footprint is smaller. Here’s what our process looks like from your first call to the day the certificate of occupancy comes through.
Stage 1: Site walk and feasibility, roughly one week. We look at where the structure can legally sit, how utilities will reach it, and whether your lot has room for the staging and drainage it needs. You’ll decide on square footage and a rough layout at this point so the plans have something real to price.
Stage 2: Design and permit filing, six to ten weeks. Plans get drawn and submitted to the Clark County Building Department. Plan review is where ADU timelines go sideways, and desert heat doesn’t speed the process up. You’ll approve the final layout and exterior finish palette before submission so nothing changes mid-review.
Stage 3: Site prep and foundation, one to three weeks. Utility trenching, grading, forms, and the concrete pour, typically scheduled early morning in summer. You decide whether the trenching path crosses any landscaping you want saved. This is also the point where homeowners often pair the job with new flatwork access, so we’ll flag it now if a heavier vehicle path is worth planning through Concrete Driveways & Concrete Work in Paradise.
Stage 4: Framing, roof, and utilities, four to eight weeks. Structure goes up, roof gets dried in, then plumbing, electrical, and HVAC rough-in. Inspections happen between each trade. You’ll pick fixtures and mechanicals while the walls are open, because changing them after drywall is where budgets blow up.
Stage 5: Finishes, punch list, and final inspection, three to six weeks. Insulation, drywall, cabinets, flooring, trim, paint, and the final walkthrough. You sign off on the punch list, we close any items on it, and the county signs off on occupancy.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between
Most of the cost spread in a detached ADU comes down to five decisions. Here’s the honest trade-off on each.
- Size and footprint: A 400 – 500 sq ft studio keeps you near the low end. A 750 – 900 sq ft one-bedroom pushes toward the top. Bigger doesn’t always rent better, but it does change how much roof, foundation, and mechanical you’re buying.
- Construction method: Stick-built on site gives you total control over layout and finishes. Modular and panelized systems from builders like Dvele or Boxabl can shorten on-site time and reduce weather risk during framing, but you’re working within their dimensions and delivery windows.
- Roof and exterior: Tile and stucco match the surrounding desert housing stock and hold up under intense sun. Metal costs more up front but shrugs off monsoon wind and sheds heat. Flat parapet roofs read modern but need careful drainage detailing.
- Mechanicals: A ducted mini-split handles 105°F summers well and lets you zone the unit. A full central system costs more but feels familiar to renters. Choose now, not during framing.
- Finishes: Builder-grade cabinets and quartz countertops keep the budget in check. Mid-tier cabinet lines and stone tile add real durability for a rental unit.
What a New Detached ADU Costs in Paradise, NV

Detached ADU construction in Paradise runs $45,000 – $130,000, with the honest middle of the market for a 600 – 700 sq ft one-bedroom landing around $85,000 – $110,000. Five things move that number:
- Square footage: Every additional 100 sq ft adds meaningful cost in foundation, roof, and mechanical capacity.
- Utility runs: The distance from your main panel and sewer or water tie-in to the new structure drives trenching and electrical cost.
- Site conditions: Sloping lots, tight side yards, and hard caliche soil all require more excavation.
- Material grade: Roofing, cabinetry, and flooring choices can swing the total by $15,000 – $25,000.
- Permit scope: A unit with its own address, kitchen, and full bath carries more review than a simpler structure.
A written estimate from us lists each line: site prep, foundation, framing, each trade rough-in, finishes, permits, and inspection allowances. Upfront pricing means the number you see is the number you pay, and 0% financing for 18 months plus $1,000 off projects over $10,000 is available. What typically sits outside the written number: landscaping repair, unexpected utility upgrades the county requires, and owner-selected furniture or appliances. Call (844) 797-4406 for an exact quote. Estimates are free.
See the difference
Before
After
Before
After
Before
AfterWhat Paradise Homes Specifically Do to This Job
Paradise is an unincorporated Clark County township, not a city, and that changes the whole build. Permits and inspections come from the county Building Department, not a municipal office, and the review schedule reflects that. The housing stock here is mostly mid-century to 1990s tract homes and low-rise condo complexes, and those lots often have utility runs and setbacks that need careful layout before a foundation is poured. The climate is the other factor: summer heat routinely pushes past 105°F, so concrete pours get scheduled at dawn and stucco curing needs attention during dry stretches and monsoon winds. If your property sits near the Las Vegas Boulevard resort corridor, staging and delivery windows can be tighter than on a quiet residential street. We handle the permit filings and coordinate inspections for homeowners across Paradise, so you’re not chasing the county yourself.
Serving Paradise, NV – Our Local Coverage Area
We serve Paradise and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Paradise

Plan on 4 – 7 months from permit filing to final inspection. County plan review eats six to ten weeks of that, construction runs three to four months, and the rest is inspection scheduling. Call (844) 797-4406 and we’ll give you a timeline for your specific lot.
Yes. A detached ADU needs Clark County Building Department permits for structure, electrical, plumbing, and mechanical. Building without them can force demolition later. We pull the permits and pass the inspections as part of the job. Call (844) 797-4406 to talk through what your lot requires.
Sometimes, but not always. If your panel and sewer tie-in are close to the build site, trenching is minimal. If they’re across the lot, expect excavation and some landscaping repair. We map the routes during the site walk so you know before you commit. Call (844) 797-4406 for that assessment.
Between $45,000 and $130,000, with most one-bedroom units landing around $85,000 – $110,000. Size, utility distance, site grading, and finish level drive the spread. Call (844) 797-4406 for a written line-item estimate. It’s free.
Every project is covered by our 730-Day Done Right Promise: if it’s not done right, we make it right. Technicians are background-checked and arrive in uniform, and calls are answered by a live person around the clock. Call (844) 797-4406 with questions before, during, or after the build.
Ready to Price Your Backyard Unit?
Call (844) 797-4406 to schedule a free on-site estimate for a new detached ADU in Paradise. We’ll check setbacks, map the utility routes, and hand you a written line-item number with the permit scope spelled out. No pressure and no vague ballpark. If the wider project grows, our Home Additions & ADU service and the Home Additions & ADU in Paradise page show the full range of work, and homeowners often pair this with Paver Driveways in Paradise for a clean new access path.
Written by the team at Groundwork Construction Co.