ADU Site Prep & Utilities in Paradise, NV: What It Takes and What It Costs
Site prep and utility work for an accessory dwelling unit in Paradise typically runs $45,000 – $130,000 when it covers grading, the pad, a new water and sewer lateral, an electrical service upgrade, gas, and the trenching and inspections that tie them together. Plan on four to eight weeks of site and utility work before framing starts, longer if a sewer tap needs county approval or the service upgrade queues with NV Energy. Call (844) 797-4406 and we’ll walk your lot and give you a written line-item scope.
How we run a Paradise ADU site and utility job, stage by stage
This isn’t a single afternoon of digging. It’s a sequence where each stage has to pass before the next one starts, and knowing the order is half of keeping a build on schedule.
- Stage 1 – Site walk and utility locate (day 1). We mark the build envelope, call 811 to flag existing lines, and pull the parcel record to confirm setbacks and what’s already buried. You decide the ADU footprint and whether it sits detached, over a garage, or attached. Anything within a few feet of a septic field or an existing lateral changes the plan right here.
- Stage 2 – Clearing, grading, and erosion control (days 2 – 5). We strip vegetation, cut and fill to grade, and set silt fencing and dust suppression before the pad is built. This is where the desert ground matters: caliche and hardpan may need ripping or over-excavation. We confirm the pad elevation against drainage away from the main house.
- Stage 3 – Trenching and underground rough-in (days 5 – 12). Water, sewer, gas, and electrical conduit go in the same trenches where code allows, inspected before backfill. You lock in fixture locations and panel placement now, because moving a drain after the slab is poured is expensive. Quality materials from partners like Belgard come in for any hardscape around the pad.
- Stage 4 – Pad, slab, and utility connections (days 12 – 20). We pour the foundation or slab, set anchor bolts, and make the physical connections to the main service, meter, and sewer. Concrete is scheduled for early morning in summer heat, and curing time gets protected with the right moisture regime.
- Stage 5 – Inspections and service activation (days 20 onward). Clark County inspections on framing, electrical, plumbing, and gas clearance come next, then meter set and utility activation. You sign off on the final walkthrough and we hand you the as-built drawings and the 730-Day Done Right Promise in writing.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices that decide how your ADU site work turns out
Most of the money in site and utility work hides in decisions made before the concrete truck arrives. Here’s where we spend the most time with homeowners.
- Detached vs. attached footprint. A detached ADU on a large lot means a longer sewer, water, and electrical run, and more trenching, which pushes cost toward the high end. Attaching it to the main house can shorten those runs but complicates the foundation and main-house tie-in.
- Electrical service size. A 100-amp subpanel may cover a small ADU, but a unit with electric range, heat pump, and EV charging is a 200-amp conversation. The upgrade, the trench, and the meter pedestal are real line items, so decide the intended use before we size it.
- Water and sewer connection type. Tapping the public main is the simplest and fastest to inspect. A separate septic or a long private lateral adds cost and a percolation review; we tell you which applies when we walk the lot.
- Utility route and trench depth. Trenching across a driveway or under a hardscape costs more than trenching over open dirt. Concrete driveways and walkways crossed by a utility run need saw-cut, removal, and restoration.
- Pad and foundation type. A monolithic slab is the budget option. A stem-wall or engineered foundation runs higher but handles sloping lots and heavier soil better. Belgard or Unilock hardscape around the finished unit is a separate pick.
What ADU Site Prep & Utilities costs in Paradise, NV

Our typical site and utility scope in Paradise lands between $45,000 and $130,000. That’s for site work and the utility connections, not the finished dwelling. Here’s how the line items usually break down.
| Line item | Typical range |
|---|---|
| Clearing, grading, erosion control | $4,000 – $12,000 |
| Foundation or slab | $9,000 – $28,000 |
| Water and sewer lateral | $7,000 – $25,000 |
| Electrical service upgrade and trench | $6,000 – $22,000 |
| Gas line and connections | $2,500 – $8,000 |
| Inspections, permits, engineering | $3,000 – $10,000 |
What pushes a job to the high end: a long detached run, caliche that needs over-excavation, a 200-amp service upgrade, a utility route under an existing driveway, and engineered foundations on a slope. What keeps it low: a compact attached footprint, short utility runs, straightforward sandy soil, and an existing panel with spare capacity.
What’s included in a written estimate: the full scope with line-item pricing, the Clark County permit applications we file, engineering where required, inspections, and cleanup. What typically isn’t: the finished ADU itself, landscaping beyond the site area, and any utility-company connection fees assessed by the provider, which we show separately. Call (844) 797-4406 for an exact quote – estimates are free and come with a design consult.
See the difference
Before
After
Before
After
Before
AfterWhat Paradise specifically does to a site and utility job
Paradise is unincorporated Clark County, not a city, so every permit and inspection runs through the county Building Department rather than a municipal office, and that changes both the paperwork and the inspection scheduling on a site and utility scope. The housing stock mostly dates to the mid-century through the 1990s as tract homes and low-rise condos, with pockets of high-rise resort construction along Las Vegas Boulevard. On older Paradise lots, we routinely find a tired 100-amp service, undersized or cast-iron laterals, and a panel that can’t carry another dwelling, so the utility work is as much about repair as new build. Extreme summer heat over 105°F pushes concrete pours and trenching to early morning, and the dry climate plus seasonal monsoon dust affects curing and site dust control on every job. Because a big share of Paradise work sits in the resort corridor, staging near casino operations can mean tight swing or after-hours windows. We serve all of Paradise and the surrounding valley. This scope is usually part of a full Home Additions & ADU in Paradise, and homeowners often pair the final hardscape with Concrete Driveways & Concrete Work in Paradise. You can see the broader Home Additions & ADU service and the full Paradise service area, or if the approach calls for pavers, Paver Driveways in Paradise.
Serving Paradise, NV – Our Local Coverage Area
We serve Paradise and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – ADU Site Prep & Utilities in Paradise

Expect four to eight weeks from the first dig to utility activation, with the longest stretch usually the county inspection schedule and the service upgrade queue. Call (844) 797-4406 for a realistic date range based on your lot.
Yes. Because Paradise is unincorporated Clark County, work on the site, foundation, and utilities requires county Building Department permits and inspections. We handle the filing and coordinate each inspection stage.
Sometimes. If your existing panel has spare capacity and the ADU’s load is modest, we can tie in a subpanel and skip a new service. A unit with a heat pump, electric range, and EV charging almost always needs the 200-amp upgrade.
A long detached footprint, utility runs under an existing driveway, hard caliche soil, a full service upgrade, and engineered foundations on a slope. That’s why the range runs $45,000 – $130,000. Call (844) 797-4406 for a line-item quote.
Every project we complete is backed by our 730-Day Done Right Promise – if it’s not done right, we make it right. You get those terms in writing before any digging starts.
Get a free estimate for your Paradise site and utility scope
Before you commit to an ADU build in Paradise, get the site work and utilities priced in writing. Call (844) 797-4406 – a live person answers, day or night – and we’ll schedule a free on-site estimate with a design consult, walk the lot with you, and hand you an upfront, no-surprise number you can plan around. Upfront pricing, no change orders, and the 730-Day Done Right Promise behind it.